The Court of Appeals deals Indiana Gasification, LLC a Setback

Rockport-IG.jpgIn Indiana Gas Company, Inc. and Southern Indiana Gas and Electric Company, et al. v. Indiana Finance Authority  and Indiana Gasification, LLC, the Indiana Court of Appeals reversed the Utility Regulatory Commission's order approving a Substitute Natural Gas Purchase and Sale Agreement (Contract) between the IFA and IG, in a 2-1, 42-page opinion.

Here is the opinion.  Indiana Gas Company, Inc. and Southern Indiana Gas and Electric Company.pdf

The Indiana Finance Authority and Indiana Gasification, LLC executed a contract in January 2011 that details the sale and purchase of substitute natural gas that IG plans to produce at a $2.7 billion Rockport plant, with delivery set to begin in the first quarter of 2016.

The IFA and IG sought approval of the contract by the Indiana Utility Regulatory Commission and requested that the commission order Indiana regulated gas utilities to enter into utility management agreements with IFA so that IFA could pass proceeds and costs to retail end use customers through the utilities, if necessary. The commission approved the contract in November 2011. Under the terms of that contract, utility customers across the State would reimburse the IFA for any losses it incurred.

The opinion defined the issues as: (1) Whether the Commission erred in approving the Contract when the Contract defined “retail end use customer” in a manner contrary to the statutory definition of the same term. (2) Whether the Commission exceeded its jurisdiction when it approved the Contract. (3) Whether the Utilities and the Industrial Group have standing to appeal the Commission’s approval of the Contract.

The commission didn’t address the scope of the term “retail end use customer” and found that it could be addressed at a future time. The industrial group filed a petition for reconsideration, arguing that industrial transportation customers were exempt from being classified as retail end use customers under statute and did not have to pay the pass-through costs of the substitute natural gas under the contract. The utilities and citizens groups also appealed.

The Court concluded that (1) the Utilities and the Industrial Group’s claims are justiciable; (2) the Commission did not exceed its jurisdiction when it approved the Contract; and (3) the Contract’s definition of "retail end use customer" inappropriately included industrial transportation customers, even though the Legislature did not intend industrial transportation customers to be subject to the SNG Act as retail end use customers.

The Court reversed the IURC order approving the contract because the contract’s definition of “retail end use customer” did not conform to the General Assembly’s intent under the SNG Act. The majority found industrial transportation customers are not subject to the SNG Act as retail end use customers.

Indiana's Smoking Ban: the 40th State to Ban Smoking in Public Places

smoking ban sign.jpgThis could be environmental law - it could be labor and employment - Indiana's smoking ban became effective on July 1, 2012.  Individuals and establishments found in violation of the law can be fined or be subjected to a civil action. IC 7.1-5-12 et seq.

The law states that with certain exceptions, smoking is prohibited in: (1) a public place. (2) place of employment. (3) vehicle owned, leased, or operated by the state if the vehicle is being used for a government function. (4) the area within eight (8) feet of a public entrance to: a public place; or a place of employment.

A "public place" is defined as "an enclosed area of a structure in which the public is invited or permitted." A "place of employment" is defined as "an enclosed area of a structure that is a place of employment. The term does not include a private vehicle."

In addition, discrimination, discharge, refusal to hire, and retaliation are prohibited against persons who report a violation or exercise their rights under the smoking ban.

The "owner, operator, manager, or official in charge of an establishment or premises" in which smoking is allowed must post "conspicuous signs" in the establishment that read "WARNING: Smoking Is Allowed In This Establishment" or other similar language.

Covered employers and operators of public places in Indiana must inform their current and prospective employees of the smoking prohibition and remove all ashtrays and smoking paraphernalia from their premises (unless the display of ashtrays or other smoking paraphernalia is intended only for retail sale).

Employers and operators of public places must post conspicuous signs at each public entrance that read "State Law Prohibits Smoking Within 8 Feet of this Entrance" or other similar language.  In addition, the "owner, operator, manager, or official in charge of an establishment or premises" in which smoking is prohibited must post "conspicuous signs" with similar language.

If an individual is smoking in violation of the ban, the "owner, operator, manager, or official in charge of an establishment or premises" must ask the individual to refrain from smoking and, if that fails, cause the individual to be removed from the public place.

Enforcement of the law can be carried out by Indiana’s Alcohol & Tobacco Commission, the State Health Department, local health departments, and law enforcement agencies, among others. These entities may inspect premises that are subject to the new law to ensure compliance and fine and bring a civil action against those found not in compliance.

There are 11 exemptions which include bars, taverns, horse racing tracks, cigar bars, casinos, riverboats, and hookah bars. Also exempted are not-for-profit private clubs and fraternal organizations.

VIM Recycling: IDEM Prevails in Contested $150,000 Fine for Failure to Meet Cleanup Deadline

VIM.jpgThe Indiana Department of Environmental Management filed a lawsuit against VIM roughly three years ago, contending it was improperly accepting waste wood containing glues, resins and other substances at its facility near Elkhart. A settlement was reached, but VIM was fined $150,000 after it failed to meet a June 2011 deadline to remove the wood.

The Elkhart Superior Court rejected an April 2012  request by the former wood recycling plant operator that the $150,000 fine against the now defunct company be waived. VIM’s operator, Ken Will, the Court last month to review its January order.

The Attorney General’s Office and IDEM filed suit against VIM in December 2009 over a large pile of industrial wood waste piled on the wood recycler’s grounds, west of Elkhart. State officials alleged that VIM illegally accepted the material, lacking the proper state permit, and had sought its removal. 

EPA also monitored the site, as a result of smoldering and burning wood piles.   

A settlement was reached requiring the gradual removal of the wood, but VIM missed the June 2011 deadline leading to the $150,000 fine.  Soil Solutions, which bought out VIM in July 2011, actually got rid of the disputed wood, not VIM or Will. 

In addition to the $150,000 fine for the six months VIM had been out of compliance with an accord to get rid of a disputed pile of wood waste, VIM has to pay $2,800 in attorney fees.  Will said in his response that the now defunct firm lacked money to pay the penalty.  The AG's office apparently intends to pursue collection, but likely stands behind other creditors.

Gary vs. IDEM and Hobart: Improving Water Quality Costs Gary a Customer

hobart.jpgYou wouldn't think that a municipal corporation would want more wastewater to treat that it already has, but Gary does. 

Hobart has been paying Gary for many years to treat its wastewater.  This led to an Indiana Court of Appeals decision this past week.  Gary vs. IDEM and Hobart.pdf

The City of Hobart's wastewater is currently treated both at Gary's wastewater treatment facility and at its own, aging Nob Hill wastewater treatment facility. Hobart pays Gary for its use of Gary's facility. Hobart's Nob Hill facility discharges into a tributary of the Deep River and consistently struggles to stay within its permit limits. Deep River is an impaired water source for mercury.  

In 2004, Hobart requested a permit to construct a new 4.8 million gallon per day wastewater treatment plant. The proposed plant would allow it to shut down the Nob Hill facility and disconnect from the Gary facility.  Also in 2004, IDEM issued the requested an NPDES permit, granting Hobart permission to operate a new wastewater treatment plant to be constructed along the Deep River. The permitted mercury limits for the proposed Hobart facility are a daily maximum limit of 3.2 parts per trillion (ppt) and a monthly average of 1.3 ppt per day. These limits are substantially less than the limits currently permitted at the Gary facility. Because the new Hobart facility will not utilize combined sewer overflows, it would completely avoid the discharge of untreated sewage. 

Shortly after IDEM issued a permit for the construction of the Hobart facility, Gary filed a petition for administrative review of the Hobart permit with the Indiana Office of Environmental Adjudication. On January 19, 2010, the environmental law judge issued its findings of fact, conclusions of law, and final order in favor of IDEM and Hobart. The environmental law judge concluded that the mercury discharge limits in the Hobart permit would result in an overall improvement in water quality, and IDEM's decision to issue the permit complied with applicable law. 

Gary then filed a petition for judicial review in Marion Superior Court. After briefing and oral argument, the trial court issued its findings of fact and conclusions of law on March 26, 2011. As is noted in the trial court’s findings and conclusions, the paramount issue in this case is the parties’ interpretation of IDEM’s antidegradation requirement for outstanding state resource waters (OSRW). 

Gary then appealed the Marion Superior Court's order affirming the order of the Office of Environmental Adjudication, which upheld the Indiana Department of Environmental Managements (IDEM) decision to issue a permit to the City of Hobart to operate a new wastewater treatment plant. 

The Court of Appeals consolidated Gary's issues.  First, whether IDEM's interpretation of 327 IAC §5-211.7 was reasonable; and, II; and second, whether IDEM' s decision to issue the permit was arbitrary and capricious and not in accordance with the law or is unsupported by substantial evidence.  The Court of Appeals affirmed the Marion Superior Court's order. 

The Court said that IDEM’s interpretation of 327 IAC §5-2-11.7(a)(2) was reasonable in that it only required Hobart to comply with subdivision §11.7(a)(2)(A) and (B), but not §11.7(a)(2)(C), in its decision to issue the permit. And, although the Hobart permit allows a new source for discharge of mercury, because Hobart will be able to close its non-compliant Nob Hill Plant and treat its wastewater more effectively than it is currently treated by Gary’s facility, the Hobart permit will result in an overall environmental benefit to and will not cause a significant lowering of water quality in Lake Michigan and its tributary, the Deep River.

Town of Avon v. West Central Conservancy District: Defining a Watercourse

watercourse.jpgThe Indiana Supreme Court has issued its decision in Town of Avon v. West Central Conservancy DistrictAvon v. WCCD.pdf  This is a Home Rule case, with an extensive discussion of the meaning of "watercourse" under Indiana law. Chief Justice Shephard spoke for the Court.

The Washington Township and the West Central Conservancy District (WCCD) owned property within the Town of Avon's boundaries that overlay an underground aquifer. After the Township and WCCD began exploring the possibility of drilling wells into the aquifer in order to withdraw water and sell it to third parties, the Town passed an ordinance that (1) prohibited taking water from a watercourse for retail, wholesale, or mass distribution unless done on behalf of the Town, and (2) defined a watercourse as any body of water whether above or below ground.

The Township and WCCD filed complaints challenging the ordinance's validity under the state's Home Rule Act. The trial court granted summary judgment for the Township and WCCD. The Indiana Court of Appeals affirmed.

In 1907, the Indiana Supreme Court defined a watercourse to mean “a channel cut through the turf by the erosion of running water, with well-defined banks and bottom, and through which water flows, and has flowed immemorially, not necessarily all the time, but ordinarily, and permanently for substantial periods of each year.”   The test is whether there is a substantial existence, unity, regularity, and dependability of the water's flow along a distinguishable course.

The Indiana Code provides that the term watercourse “includes lakes, rivers, streams, and any other body of water.” IC §36–9–1–10. No surprise: the litigants disagreed as to whether an aquifer may be properly categorized as “any other body of water” under this definition.

Avon contends that the word “any” dictates an expansive scope for this provision, and the provision applies to “ ‘each,’ ‘every,’ and ‘all’ bodies of water, wherever located.” (Appellant's Br. at 12.) If true, this definition would include all aquifers.  The Court thought that Avon's suggested interpretation was too broad.

Indiana’s common-law definition of watercourse has consistently held that whether a body of water has defined banks, bottom, and channel is not conclusive in determining if that body of water is a watercourse. The phrase “any other body of water” in IC §36–9–1–10 refers to any other body of water satisfying Indiana's common-law definition of a watercourse. A body of water's similarity to a lake, stream, or river would be informative, but not dispositive.  

The Court noted that the Indiana Code defines an aquifer, for purposes of its Water Resource Management statutes, as “an underground geologic formation that: (1) is consolidated or unconsolidated; and (2) has the ability to receive, store, and transmit water in amounts sufficient for the satisfaction of any beneficial use.” IC §14–25–7–1. “This definition seems to indicate some of the characteristics we might look for in a watercourse.”

The Court's analysis led it to conclude that the White Lick Creek Aquifer is a watercourse under Indiana law, and not the “lost water” the Court addressed in earlier cases. The water in those earlier cases percolated the ground “below the surface of the earth, in hidden recesses, without a known channel or course." 

The Supreme Court reversed, holding (1) the aquifer at issue was a watercourse under Indiana law; (2) the Home Rule Act permitted the Town to regulate another political unit's attempt to withdraw water from the aquifer; and (3) the Town's proposed regulation was not preempted by statutes authorizing the Department of Natural Resources to regulate aquifers.

Indiana Waste Treatment Company Charged with Violating the Clean Water Act

seal[1].jpgTierra Environmental and Industrial Services, Inc., a centralized waste treatment facility in East Chicago, its owner and a manager were charged with conspiracy and felony violations of the Clean Water Act in a seven-count indictment returned by a federal grand jury, on Friday, November 4.  

Tierra Environmental, owner Ronald Holmes and manager Stewart J. Roth have been charged with illegally discharging wastewater into the sewers of the Hammond Sanitary District from a closed facility.

Tierra is a centralized waste treatment facility that charges customers to dispose of their polluted wastewater.   Tierra advertised itself as specializing in spill remediation; bio-waste cleanup; waste brokerage; hazardous and non-hazardous transportation services; industrial wastewater/sludge removal and disposal; grease trap cleaning and tank cleaning for hotels and restaurants; and liquid waste transportation and disposal from food processors, distributors and manufacturers in all industries.   Tierra collected both hazardous and non-hazardous liquid wastes from customers, using a number of vacuum trucks and tanker tractor-trailer trucks.   Tierra had facilities for limited storage, separation and solidification of non-hazardous wastes.  

According to the indictment, Tierra’s East Chicago facility did not hold a permit to discharge industrial waste to the East Chicago Sanitary District’s sewer system and the facility’s connection to that sanitary sewer system had been sealed shut.   The company therefore had to transport wastewaters it collected from customers to other facilities for final treatment and/or disposal.     

The indictment alleges that the conspiracy was undertaken for the purpose of avoiding expenses associated with treating and/or paying other facilities to lawfully treat, store, or dispose of wastewaters collected from customers.   The indictment also alleges that the defendants conspired to achieve this objective by transporting wastewater to a shut-down, unpermitted facility located  in Hammond that was owned and/or controlled by Ronald Holmes.   There, the wastewater was discharged directly to the Hammond Sanitary District’s sewer system.

The Clean Water Act makes it a felony to knowingly discharge trucked or hauled pollutants into a publicly-owned treatment works (POTW) from a discharge point not designated by the POTW.

If convicted, Holmes and Roth face up to five years in prison on the conspiracy count and three years on each of the Clean Water Act counts, as well as a criminal fine of up to $250,000 for each count.   The company may also face fines and probation.

The case was investigated by the Northern District of Indiana Environmental Crimes Task Force, including agents from the U.S. Environmental Protection Agency’s Criminal Investigation Division, the Indiana Department of Environmental Management- Office of Criminal Investigations, the U.S. Department of Transportation, Office of Inspector General, and the U.S. Coast Guard Criminal Investigative Service.  

Fiedler v. Indiana Office of Environmental Adjudication: Time for Filing

Indiana Court of Appeals.jpgIn a short memorandum decision, not for publication, the Indiana Court of Appeals held that an Order from LaGrange County properly dismissed a petition for judicial review.

In August and September 2009, the Indiana Office of Environmental Adjudication (OEA) received petitions from property owners (Petitioners), including Fiedler, asking the OEA to review a construction permit that the Indiana Department of Environmental Management (IDEM) had issued to the LaGrange County Regional Utility District (LaGrange) so that LaGrange could install a sanitary sewage collection and transmission system near Shipshewana Lake in LaGrange County, Indiana.

LaGrange and the Petitioners filed competing motions for summary judgment. The OEA issued findings of fact, conclusions of law, and a final order, dismissing the Petitioners' petition for review. The OEA sent a copy of the Final Order to the Petitioners' representatives by certified mail on May 6, 2010, and Fiedler received the Final Order on May 11, 2010.

Then, on June 9, 2010, Fiedler filed a petition for judicial review of the OEA's Final Order. His petition did not contain language stating that it was submitted under oath or by affirmation, or that the representations in the petition were true. IDEM filed a motion to dismiss Fiedler's petition.

IDEM claimed, among other things, that Fiedler had failed to meet the jurisdictional requirements of I.C. § 4-21.5-5-5, which requires a plaintiff to file a petition for review within 30 days of service of the notice of agency action that is the subject of the petition. Subsequently, the trial court held a hearing on the motion to dismiss and dismissed Fiedler's petition.

On appeal, Fiedler argued that the trial court did have jurisdiction over his claim because he filed it within a timely manner, as required by I.C. § 4-21.5-5-5.  Indiana Code § 4-21.5-5-5 identifies the required procedure for filing a petition for review when it states that "[e]xcept as otherwise provided, a petition for review is timely only if it is filed within thirty (30) days after the date that notice of the agency action that is the subject of the petition for judicial review was served." Further, a person who "fails to timely object to an order . . . waive[s] the [] right to judicial review. . . ." I.C. § 4-21.5-5-4.

Fiedler claimed that he filed his petition for judicial review within the 30 day time limit required by I.C. § 4-21.5-5-5, but the Court of Appeals did not agree with this argument.  It found that he filed his petition one day after the time limit.

The OEA sent a copy of the Final Order to the Petitioners' representatives, including Fiedler, by certified mail on May 6, 2010, which qualifies as the commencement of service under I.C. § 4-21.5-3-2. Because the Court does not include the day from which the designated time begins to run, though, the first day for the purposes of computing the 30 day time limit was May 7, 2010. See I.C. § 4-21.5-3-2(a).  Fiedler in actuality had a 33 day time limit because he received notice through the United States mail. See I.C. § 4-21.5-3-2(e). Under those standards, Fiedler was required to file his petition by Tuesday, June 8, 2010. However, he did not file his petition until June 9, 2010.

Fiedler made an additional argument, which the Court of Appeals rejected. He argued that the Court should only include business days in computing the time limit.  However, the Court concluded based on I.C. § 4-21.5-3-2 that the time period the Code is referring to is the 30-day time limit, not the 3 day extension. Indiana Code section 4-21.5-3-2 declares that "[a] period of time under this article commences when a person is served with a paper. . . ." The 30-day limit commences with the service of a paper, but not the 3-day extension.  Therefore, Fiedler did not timely file his petition. See I.C. 4-21.5-5-4.

Indiana Supreme Court: Location of Risk Crucial to Determination of State Law Coverage

indianaseal.jpgIn National Union Fire Insurance Co. v. Standard Fusee Corp., Ind., No. 49S04-1006-CV-318  (December 29, 2010) the Indiana Supreme Court ruled that a company's principal place of insured risk is the most important factor in determining which state law governs multi-state insurance contract.  Justice Frank Sullivan Jr. wrote the opinion for the Court. 

The court said that by locating its headquarters at an insured site in Maryland, the policyholder made the site its principal location. 

Standard Fusee Corp., makes emergency signal flares and related products.  It leased facilities in Indiana and California. After tests showed contamination at the facilities by perchlorate, a chemical used in the production of flares, the company sought a declaratory judgment that several insurers from which it had purchased comprehensive general liability policies were required to defend and indemnify it against environmental liabilities arising from the contamination. 

The trial court granted Standard Fusee partial summary judgment, holding that Indiana law governed interpretation of the policies. The Indiana Court of Appeals reversed, adopting a “site-specific” approach to the choice-of-law issue and ruling that Indiana law governed interpretation of the policies with respect to the Indiana site and California law with respect to the California site. 

Both Standard Fusee and the insurers petitioned the Indiana Supreme Court to vacate the appeals court's opinion and apply a uniform contract interpretation approach. Standard Fusee argued that Indiana law governs policy interpretation; the insurers contended that Maryland law applies. 

The Indiana Supreme Court said that because Standard Fusee sued in Indiana, Indiana's choice-of-law rules apply. The court said a review of the state's case law shows that a uniform approach is more consistent with its jurisprudence in resolving choice of law issues than a site-specific approach and should apply in cases involving multi-site, multi-state insurance policies. 

In choice-of-law cases involving contracts, the court said, Indiana applies the law of the state in which the transaction is “most closely associated.” Under the Restatement (Second) of Conflict of Laws Section 188, certain contacts must be considered in making that determination: (1) the place of contracting, (2) the place of negotiation of the contract, (3) the place of performance, (4) the location of the subject matter of the contract, and (5) the domicile, residence, nationality, place of incorporation, and place of business of the parties. 

While none of the factors are determinative, the court said, the overall number and quality of contacts favor Maryland over Indiana. The court held that the substantive law of Maryland applies to the entire dispute.

In analyzing the respective contacts with Indiana and Maryland, the trial court found four of the five factors listed in Section 188 inconclusive while one, the place of performance, clearly pointed to Indiana. Rejecting that analysis, the Indiana Supreme Court said that if the principal location of the insured risk can be identified, under section 193 of the Restatement it is given more weight than any of the other factors in making this determination. 

State Auto vs. Flexdar and the Pollution Exclusion

This is an insurance coverage dispute involving the interpretation of a pollution policy exclusion.

Flexdar, Inc., manufactured rubber stamps and printing plates at its factory in Indianapolis. Flexdar's machinery employed the chemical solvent trichloroethylene, which leaked from the factory premises and contaminated subsoil and groundwater.

The Indiana Department of Environmental Management ordered Flexdar to investigate the contamination and informed Flexdar that it could be liable for the costs of cleanup. Flexdar requested defense and indemnification from its commercial general liability insurer, State Automobile Mutual Insurance Company.

State Auto filed this action seeking declaration that it owed no coverage. State Auto invoked a policy exclusion barring coverage for claims resulting from the escape of "pollutants." The trial court entered summary judgment in favor of Flexdar. The trial court found that State Auto's pollution exclusion was ambiguous and unenforceable and thus did not preclude coverage.

The Indiana Court of Appeals agreed and affirmed the judgment of the trial court.

Motors Liquidation Company - formerly GM - Bankruptcy Settlement

GM.jpgOn October 20, 2010, the US Environmental Protection Agency, the US Justice Department, and the Unites States Attorney for the Southern District of New York, along with the states of Indiana, Delaware, Illinois, Kansas, Louisiana, Massachusetts, Michigan, Missouri, New Jersey, New York, Ohio, Pennsylvania, Virginia, Wisconsin and the Saint Regis Mohawk Tribe announced that Motors Liquidation Corporation has agreed to resolve its liabilities at 89 sites in 14 states across the country for approximately $773 million.

The agreement settles certain of the claims of the US, the states, and the tribe in the General Motors Corporation bankruptcy case relating to liabilities under the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA, also known as Superfund), the Resource Conservation and Recovery Act (RCRA), and the Clean Air Act (CAA).

The bankruptcy settlement will establish a $773 million Environmental Response Trust (the Trust) to conduct, manage, and fund cleanup at the 89 GM owned sites where MLC has liabilities. The bankruptcy settlement also envisions the redevelopment of the sites in the Trust.  Find all 170 pages of the Consent Decree and Settlement Agreement here.

MLC has agreed to transfer ownership in 89 properties to an Environmental Response Trust (ERT or “Trust”). The Debtors will initially fund the trust with $773 million in cash and other assets. The Trust will perform cleanup work pursuant to budgets approved by the lead agencies and reimburse the governments. The funding represents the most likely cost of cleanup based on available information.

The Environmental Response Trust will consist of the following:

  • Minimum Estimated Property Funding Account containing $295 million;
  • Reserve Property Funding Account containing $52 million;
  • Long Term OMM Property Funding Account containing $84 million;
  • Cushion Funding Account containing $68 million;
  • Administrative Funding Account containing $232 million; and
  • Administrative Funding Reserve Account containing $40 million.

The Earlier Cinergy Decisions and Clean Air Act Violations as an Occurrence

In 1999, the United States, three states, and two environmental organizations filed a lawsuit in Federal court against Cinergy for alleged violations of the Clean Air Act (hereinafter referred to as “the underlying Federal litigation.”). The complaint alleges that Cinergy performed certain maintenance and repair projects at six power plants without obtaining the permits required under the Clean Air Act. Operation of the plants without installing additional air emissions containment equipment has caused increased emissions of harmful substances into the air. In the ongoing underlying Federal litigation, the plaintiffs seek to compel Cinergy to install equipment to reduce future emissions of pollutants and to prevent resulting future environmental harm.

In October, 2000, the insurance companies filed a declaratory judgment action for a determination of their coverage obligations under the insurance policies Cinergy carried on its power plants during the relevant time periods. Proceedings in this cause have resulted in several appeals to Indiana's appellate courts. 

In Cinergy I, Cinergy appealed the denial of its motion for partial summary judgment in which the company sought an order directing AEGIS to pay the company's expenses as incurred in the defense of the underlying Federal litigation. Our supreme court held that the policies do not provide coverage for damages “in the form of installation costs for government-mandated equipment intended to reduce future emissions of pollutants and to prevent future environmental harm.” Ultimately, the court concluded, “[b]ecause the insurance policies do not provide coverage for the costs of installing such equipment, the trial court did not err in denying partial summary judgment seeking to compel payment of all costs incurred by [Cinergy] in defending all claims in the Federal lawsuit.”

Approximately four months later, the Court of Appeals court issued its opinion in Cinergy II.  In that case, the trial court entered partial summary judgment to the Insurers after concluding that Cinergy failed to establish that there was a “potential occurrence” during the 1983-84 policy term at Cinergy's Cayuga Plant.  The trial court decision was affirmed after concluding that there was neither an actual or potential occurrence under the policy at issue, as that term was interpreted by the Indiana Supreme Court in Cinergy I. 

After the Cinergy I and Cinergy II decisions issued, the insurers then moved for summary judgment seeking an order declaring that they have no obligation to defend or indemnify Cinergy for any of the claims being adjudicated in the underlying Federal litigation. Cinergy filed a motion to postpone any indemnity determination until the claims in underlying Federal litigation are resolved. 

PR Mallory v. American Casualty and the Failure to Provide Timely Notice

The Indiana Court of Appeals, in an opinion written by Judge Elaine Brown, says a 20 year lag between discovery of an environmental problem and notice to the insurer is fatal to coverage.  This appears to be the first reported decision in which the Indiana appellate courts have affirmed summary judgment on the issue of late notice in the environmental coverage context.

In P.R. Mallory & Co., Inc. v. American Casualty Co., the Court of Appeals affirmed a trial court order granting summary judgment to an insurer - based on the insured’s failure to provide notice regarding environmental liability at a site in Attica for almost 20 years.  The appellate court held that notice to the insurers of the environmental claim swas unreasonably late, and that the insured failed to rebut the presumption of prejudice with any evidence.

Here's the timeline:

• 1950-1963: RMC dumps waste at “Site A,” which is on property owned by RMC in Attica, Indiana;

• 1963-August of 1980: RMC dumps waste at “Site B,” which is on property owned by RMC in Attica; 

• 1995-1996: RMC learns of extensive contamination at its Attica site (which, again, it owns) and begins on-site cleanup, during which RMC learns that it has contaminated groundwater; 

• March of 1999: EPA finds “a release of hazardous waste into the environment from the Attica facility”;

 • August of 2000: RMC files suit against multiple insurance companies, including the parent company of two insurers at issue here.

No surprise, the parties disagreed as to when notice was given. The Plaintiffs argue that notice was given to the insurance companies in August 2000 when the insured filed an Amended Complaint for Declaratory Judgment and Breach of Contract. The insurers argue that notice was not given until 2003. The Court said even if notice was as early as 2000, it was still too late.  The Plaintiffs had knowledge of an occurrence long before they notified the insurers and the delay in notification of the occurrence constituted unreasonably late notice.

The Court of Appeals found that the insured had knowledge of an occurrence long before it notified insurers and the delay in notifying its insurers of the occurrence constituted unreasonably late notice; and the insured's unreasonable delay was presumed to have prejudiced the insurance companies.

The court also said that notice is a threshold requirement which must be met before an insurer is even aware that a controversy or matter exists and it requires the cooperation of the insured. Further, the Court noted that the notice requirement is "material, and of the essence of the contract" and that “the duty to notify an insurance company of potential liability is a condition precedent to the company's liability to its insured.”

Indiana courts have previously interpreted the phrase “as soon as practicable” in the context of the notification provision to require “reasonable notice.”  Based upon the designated evidence, the Court held that the Plaintiffs had knowledge of an occurrence before they notified the insurance companies and that the delay in notification resulted in prejudice to the insurance companies.

So, the moral of the story: when you've got a problem ... give notice to your insurer and do it early on. Don't wait 20 years, don't wait six months.  Get the insurance company in the game.

Cinergy v. St. Paul Surplus Insurance: Triggering the Duty to Defend

On October 28, 2009, the Indiana Court of Appeals, in an opinion written by Judge Paul Mathias, upheld a summary judgment ruling in litigation brought by several insurance companies finding that the insurers had no obligation to defend, indemnity, or otherwise provide coverage for energy companies with respect to alleged Clean Air Act violations and penalties, because “preventing future emissions and environmental harm is not an ‘occurrence’ under the applicable insurance policies”.  The Indiana Supreme Court denied transfer a few days ago, leaving the Court of Appeals decision intact. 

In an effort to improve and control ambient air quality, Congress enacted the 1977 Amendments to the Clean Air Act.  The amendments created the new source review program, which is a permitting program for new or modified, major, stationary sources of air pollution in nonattainment areas.  Under the program, any new project or modification to an existing project that would emit more than a threshold amount of a pollutant for which that region has not attained the National Ambient Air Quality Standards must apply for a permit to construct and operate that pollution source.

A non-attainment area is an air quality control region that has not met the National Ambient Air Quality Standards.

The Court held that: (1) that costs associated with the insured's surrender of emissions allowances did not constitute an occurrence; (2) preventing future emissions and environmental harm was not an occurrence; and (3) that the trial court was not required to postpone an indemnity determination pending the outcome of federal litigation.

One outcome of the Supreme Court’s decision against granting transfer here is that facilities that emit carbon dioxide may decide to procure liability insurance that specifically addresses greenhouse gas emissions. We'll see.